Project Name: Brownfield site for commercial development
Location: Tampa, FL
Client Type: Manufacturing/ Commercial
Size: 158 acres
Services Provided:
- Soil and groundwater quality assessment
- Pre-Demolition asbestos report
GBTS started this project with an SAR (Phase I) assessment (2019)
- Expanded Phase II (2019)
- SSAR (2021)
- Supplemental Site Assessment (Jan 2022)
- SARA (June 2022)
- Site Assessment Report Addendum (Nov 2022)
- ISR Workplan (Nov 2022) Interim Source removal
- IS Report (Feb 2023)
The Propertyowner was preparing a building permit plans for the construction of a commercial soft drink manufacturing and distribution complex. The proposed complex would be connected to the municipal water and sewer systems.
GBTS found arsenic in onsite soils and groundwater. We recommended the following:
- Affected soils be excavated as part of an Initial Source Removal (ISR) prior to the start of construction.
- Implementation of Soil Management, Health & Safety and/or Air Monitoring Plans during excavation and redevelopment construction activities.
- Groundwater Natural Attenuation Monitoring Only Plan (NAMOP) for a minimum of 1‐year.